Photo above: to the right of the school sign, the first shelter is the temporary church with a silver plastic tarp for a roof and behind the church is a new green metal roof building. The green roof building is the new 3 room classroom building for the primary school. Cyclone Pam destroyed the church and school in March.
I was very excited on December 23, to go up to Green Hill Teouma and check on the progress of the new building. Since the rains have started, the road to Green Hill is an hour long 4 wheel drive mud adventure. A group of nine men have been working for a several weeks on the new school building and I was anxious to see what they had accomplished since my previous visit.
The roof is on!
It has been a challenge to build so far off the main road. Most hardware stores and suppliers will not deliver to Green Hill so we have had to use a 4WD pick-up truck to haul materials. We started in November pouring the concrete slab in severe drought conditions, which necessitated the hauling of water from 45 minutes away to mix the concrete. Then when we got ready to put on the roof, the rains started and the road is now flooded! We are happy for the rain as the community had emptied their drinking water tanks!
To this point, the new school building has been financed by ACCIR in Australia. We are so grateful for their partnership. The siding for the building and doors have already been purchased but we are lacking funds for some important items to finish it:
US$3000 – one more month of worker’s salaries
US$700 – masonite sheets for the ceiling
US$700 – timber for knockings
US$1200 – louvre window frames and glass
US$2000 – wood primer and paint
Please label donations for Green Hill School Project #5778 if you are donating through AGWM. Thank you!